The SR-55 West Price Bridge construction team is pleased to announce the railroad has granted approval to conduct work over the tracks. It will take today and tomorrow to reactivate the contractor’s team so you can expect a full schedule work to begin this Wednesday, May 8th.
Crews will begin saw cutting the existing concrete deck panels and parapets on Wednesday and the remainder of this week. Then beginning Monday, May 13th through Wednesday, May 15th, crews will remove parapet over the railroad tracks. The deck panels will then be removed beginning Wednesday, May 15th and continue through Saturday, May 18th.
We remind you the bridge is impassable to vehicles and pedestrians and all access to the structure is strictly prohibited. Safety is always the highest priority on highway projects. Please follow posted detours.
If you would like more details, please feel free to call our project hotline at 800-292-3557 or Dave Asay, Public Information Manager direct at 801-712-3030.